Tuesday, December 23, 2008

Windows and Sheetrock



Installation of window frames and Sheetrock have begun. The windows will be store-front type with metal frames. The first Sheetrock to be installed are for the exterior office walls to allow for the stucco contractor to begin.
Posted by Picasa

Friday, December 5, 2008

Interior Progress

With the roof nearly complete, work continues to escalate on the interior items. The framing is complete, the HVAC units have been installed, the duct work is underway, the Electrician is currently pulling wires for lights and outlets and some insulation has been installed. The exterior of the building is being prepared for the stucco while the site concrete is almost finished.
Posted by Picasa

What's the Caption?


We showed this picture on our Company Intranet and asked everyone to submit a caption for this photo. Here is a sample of what was submitted:

"Where is the Brake?"
"So much for the survey area."
"Oops! Missed a Spot Inside"
"Hope this is the right address"
"What did Brandon order now?!?"

Thanks to all the comedians who participated.